Engineering · Data centers · Thermal systems

Data Hall Interactive Training Studio

A data-center interactive training studio comparing air and liquid systems, redundancy and failure response through JavaScript heat balances, component-power calculations and time-dependent thermal models.

The studio pairs heat-removal calculations with separate airflow and power-transfer exercises.
Diagram in text
Rack heat
Set the IT load and rack configuration.
Air side
Size airflow or check rack-inlet mixing in Case A.
Liquid side
Follow coolant through the CDU and plant.
Resilience
Compare duty and standby paths. Test Case B power transfer.

Interactive tools

Approach and contribution

30-second case brief

From rack heat to cooling continuity.

Problem
Coordinate heat paths, airflow, capacity redundancy and cooling power through normal operation and failures.
Contribution
Developed the heat-balance, component-power, route-availability and coupled thermal-storage models, with inspectable interactive tools.
Result
Approximately 3.0°C lower inlet with containment in Case A; uninterrupted modeled coolant flow through the 60-second backed transfer in Case B.

ApproachSI heat/flow balances · component availability · event-aware integration · energy conservation · native EnergyPlus reconciliation.

Project scope and responsibility

Context
Interactive engineering training · cooling-system balances and four-zone air mixing
Role
Model formulation, engineering scenario design, calculation workflow, and interactive technical presentation
Configuration
Eight cooling architectures · generic and Vera Rubin NVL72 rack scenarios
Design basis
24 × 8 kW generic racks or 330 kW NVL72 · 110% cooling sizing allowance
Methods
Heat and flow balances · component power · thermal storage · event simulation
Evaluation
N / N+1 / N+2 / 2N / 2(N+1) · maintenance and failure states · four-zone airflow model

Cooling lab: 192 kW generic operating heat with a 110% sizing allowance, or the NVL72 preset. The integrated network comparison uses that configuration. Power-transfer and airflow exercises retain their named input cases.

Cooling systems and load basis

This interactive training studio follows rack heat through air or liquid cooling, equipment sizing and failure response. Start with the cooling architecture and operating load, then compare five engineering arrangements under one shared scenario. Equipment cards expose duty and standby groups, isolation points, power and control dependencies. Planned maintenance, unexpected failure and failure during maintenance are separate test conditions. The adjacent assessment relates the selected test to Tier I–IV objectives without assigning a Tier classification. Design-point flows, electrical demand and temperature checks remain expandable below the comparison. Eight architectures remain available, including a Vera Rubin NVL72 hardware preset based on NVIDIA’s published reference.

The generic starting case is 24 × 8 kW = 192 kW of operating IT heat. A separate 110% design allowance gives 211.2 kW of net IT-side cooling sizing duty; whole modules are rounded up from that requirement. This chosen allowance is a training input, not a universal code requirement. The operating-load control can represent part load or overload without silently changing the installed design. One NVL72 rack uses a 330 kW cabinet design basis. A selected 98% liquid capture divides it into 323.4 kW liquid and 6.6 kW residual air, with a 495 L/min published design-flow floor.

Outdoor dry bulb and dry-cooler approach determine whether the requested water supply can be produced. Water-to-air and interloop approaches then check whether that supply can cool the selected load. Required flow remains a hypothetical sizing value when a temperature path is infeasible; achieved electrical demand and heat rejection are then unavailable. Standby equipment restores service only if its physical temperature path and distribution remain available.

Interactive workspace · Cooling systems, engineering arrangements and failure response

Interactive training studio · calculated scenarios

Follow the heat.
Test the resilience.

Choose a cooling architecture, inspect its heat and flow balances, then test the cooling paths under a failure or maintenance event.

Choose a rack basis, then inspect the cooling architecture and response sequence.

CRAH · Chilled-water room cooling

Room air crosses a chilled-water coil. Fans return cooled air to the racks; the facility-water loop carries heat to the plant.

24 racks. Generic modules represent complete net cooling paths. The NVL72 case sizes the warm-liquid plant, CDU and independent room-air modules separately. Enter the net IT heat that one module can remove at the selected operating point, after its auxiliary heat is accounted for. The design allowance defaults to 110% and stays at or above 100%; N rounds this sizing duty up to whole modules. Operating load changes the heat currently generated, independently of the design allowance.

Outdoor temperature sets the dry-cooler feasibility boundary. The entered chiller/DX COP is a fixed training input, not a weather-dependent equipment curve. Try 30°C and 40°C outdoors with the same warm-water setpoint.

One scenario · five engineering arrangements

Compare what stays connected.

Capacity reserves, independent distribution and uninterrupted cooling answer different questions. Set one event below; every arrangement uses the architecture, loads, weather and module duties selected above.

Connections, isolation and operating provisions

These are explicit scenario assumptions, not properties guaranteed by a redundancy label. A checked provision means it is included in this network model. On one-route arrangements it cannot create a second route.

In a dual-route test, maintenance removes the selected item on B; the injected fault acts on A. In a single route, both act on that route. A module under maintenance consumes a spare first. Planned maintenance prepositions available replacements; an unexpected fault waits for the pickup delay. A shared header or common cooling-power loss disables both routes until the event ends. No generator or UPS is assumed here. A common power event keeps cooling off for the source interruption plus the entered restart delay.

Equipment and connections

● Connected◇ Ready spare× Isolated / unavailable

Performance on the same time axis

Five-arrangement engineering comparisonAll arrangements share one elapsed-time axis. The event interval is shaded. Select a quantity and use the results table for exact values.
Full-window results under the same scenario
ArrangementMinimum usable capacity
kW IT
Minimum actual removal
kW IT
Shortfall
kWh
Peak air bulk rise
K
Cooling duty restored
elapsed s
Air bulk recovered
elapsed s
IT curtailed
kWh

Flow interruption: Not evaluated. Module availability is not a hydraulic or airflow-continuity calculation.

Liquid / chip temperature: Not evaluated. Use the separate coupled-loop power-transfer mode for its stated boundary.

Outdoor heat rejection during faults: Not evaluated. The design-point balance below is separate from this transient dispatch model.

Equations, boundaries and interpretation

N is the whole number of duty modules required for the 110% design-sizing duty (or the edited allowance). N+1 and N+2 add one or two spares to every nonempty group on a single route. 2N duplicates the required groups on A and B. 2(N+1) gives each route its own spare in every group. A shared spare 2N+1 arrangement is not modeled.

Usable capacity is the maximum total IT heat supportable at the selected air/liquid split, after serial bottlenecks and connection states. Actual removal is limited by active IT heat in each circuit. Cooling shortfall = active IT heat − actual removal. Its integral is reported in kWh; it is not automatically stored heat. Rack shutdown reduces active demand and is reported separately as curtailed IT energy.

For the air circuit only, stored heat follows E(t + Δt) = max[0, E(t) + (air shortfall − available air recovery duty) × Δt]. Air bulk rise = E / effective air-side thermal capacity. This effective well-mixed store is not a rack-inlet or chip temperature prediction. Spare connected capacity can remove this store after pickup. Liquid shortfall is recorded as unremoved heat without assigning it to a fictitious flowing liquid inventory. A 100% liquid case therefore has no air-temperature result.

Net module duties are assumed available at the selected setpoints. Outdoor, air-coil, rear-door and CDU temperature approaches gate the relevant circuit. A feasible temperature check does not replace equipment performance curves or site design. The separate design-point balance includes auxiliary heat; the route transient tracks net IT heat only. The models share edited inputs, not unverified transient power or outdoor-rejection results.

All delays, spare dispatch, isolation behavior, loads and effective thermal capacities are training assumptions. The default 192 kW case uses three 80 kW duty paths and a 30 s pickup delay. Adding a spare can shorten a deficit without guaranteeing continuity. No cooling-capacity label alone establishes Tier III or IV.

Network calculation source ↓Open detailed power-transfer mode ↓

resilience-workspace-20261030-v1 · Equipment counts, connection assumptions and interval heat balances are included in the export.

Design-point heat paths, flows, electrical demand and assumptions
  1. 01Server air
  2. 02CRAH coil
  3. 03Facility water
  4. 04Outdoor heat rejection
IT heat192.0 kW
Air / liquid heat192.0 / 0 kW
Cooling electrical demand—
Total environmental heat release—

Air side

Required server airflow
—
Required residual room-cooling airflow
—
Required external cooling-fan power
—

Liquid and plant

Required facility-water flow
—
Required technology-liquid circulation
—
Evaporation rate (two-phase)
—
Required pump / compressor power
—

Inspect and edit the engineering assumptions

The 110% sizing allowance, 80 kW generic modules, 500/50 kW liquid/air modules, 30 s response, 150 kPa pressure rise, 65% efficiency, COP 4 and 3 kW outdoor auxiliary are selected demonstration values. They are not measured equipment performance or claims about common industry values; the NVL72 reference card identifies the sourced manufacturer values. Air uses ρ = 1.2 kg/m³ and cp = 1.006 kJ/(kg·K); facility water uses ρ = 1,000 kg/m³ and cp = 4.18 kJ/(kg·K). Enter the actual fluid properties for a selected liquid. The single-phase immersion preset uses illustrative dielectric properties of 1.6 kJ/(kg·K) and 800 kg/m³.

Flow requirements include the pump heat entering each liquid circuit. External fan heat enters the cooled air; pump work enters its respective fluid. The circuit rejection includes compressor work. Outdoor auxiliary electricity dissipates outside the fluid circuits and is added separately to the total environmental heat release. If a temperature approach is infeasible, required flows remain hypothetical sizing requirements and achieved operation is unavailable. In the NVL72 case the warm facility-water flow carries liquid-captured heat, while a separate low-temperature room-air unit uses the entered COP. Server-integral fans are already inside IT power. Rear doors are passive in this calculation; their server airflow carries the full rack heat. The two-phase value is an evaporation mass rate, not a pumping flow.

Compare the eight architecture requirements

One boundary · eight architectures

Compare the heat paths.

All rows use the current IT load, pressure rises, efficiencies and plant settings. Single-phase immersion uses the dielectric preset; two-phase immersion uses the entered latent heat. The table shows design-point requirements.

Calculated system requirements under the current assumptions
ArchitectureAir / liquid heat
kW
Server air
m³/s
Facility water
kg/s
Technology flow
kg/s
Electrical demand
kW
Plant condition
Calculation source ↓

cooling-studio-20261030-v4 · Design-point balances with a linked five-arrangement network comparison. Inspect assumptions for the complete model boundary.

NVL72 cooling through a power transfer

Case B holds IT heat at 330 kW through an assumed independent IT supply while the cooling plant loses power. Generator availability after 45 seconds and another 15 seconds of restart create a 60-second bridge. The continuity case begins at 40°C TCS supply, rather than the architecture preset’s 45°C steady design point, to examine thermal headroom below the published inlet reference.

Backing only the technology pump preserves flow but concentrates heat in the 250 L technology inventory. Backing both loops connects that inventory to a 2,000 L facility buffer, and the separate air unit removes the remaining 6.6 kW. The calculation tracks the two heat stores and finite UPS energy independently, so a large buffer cannot conceal a stopped pump or depleted battery.

Interactive tool · NVL72 backup power and coupled-loop thermal storage

Interactive NVL72 power-transfer example

Keep the liquid moving.
Keep its temperature controlled.

Compare a cooling interruption, a backed circulation pump, and backed circulation with thermal storage and residual-air cooling. Follow the coolant during the generator transfer.

The NVIDIA DSX reference ↗ describes GPU cooling using loop thermal mass during power outages. Uptime Institute's Tier explanation ↗ connects fault tolerance to the complete infrastructure. This calculation examines continuous cooling using stated power and thermal assumptions.

Cabinet heat uses the 330 kW DSX design basis per rack. The example holds IT power constant through a separate assumed IT supply. Liquid capture (98%), water-reference properties, inventory, backup capacity, pressure loss and response times are selected training inputs. Technology flow uses at least 1.5 L/min per cabinet design kW; changing operating heat alone does not reduce this design-flow floor. The continuity case starts at 40°C TCS supply, providing 5 K below the published inlet reference. The architecture preset above uses a separate 45°C steady design point. Each tool names its initial conditions explicitly.

Power and heat paths during the cooling-supply interruption
01Rack cold plates323.4 kW liquid heat
02Technology pumpUPS-backed circulation
03CDU + facility pumpUPS-backed circulation
04Mixed thermal buffer2,000 L usable
05Outdoor heat rejectionGenerator transfer + restart
Cooling UPSResidual-air cooling

Technology flow interruption—
Flowing-period peak / 45°C reference—
Cooling UPS operating load—
Nominal UPS energy for the transfer—
Facility volume for full bridge—
Liquid / room-air heat unserved—

Technology-loop flow · L/min
Technology-loop flow during cooling power transfer00125 min

Flowing technology supply · °C
Mixed-loop supply temperature while circulation is available0125 min

Assess flow, flowing supply temperature and residual-air service separately. A lower displayed temperature during an interrupted-flow case does not indicate better cooling: no supply or chip temperature is predicted during the gap. The shaded interval is the plant power outage, not necessarily a coolant-flow outage.

Fluid, power and thermal-storage inputs

Battery energy available to the cooling circuit = nominal kWh × usable fraction × conversion efficiency. Flow requires an energized pump circuit; thermal volume alone does not maintain circulation. With both loops circulating, heat is exchanged between the technology inventory and facility buffer through the modeled CDU. With only the technology pump running, that heat accumulates in the smaller technology-loop inventory.

The two well-mixed inventories obey CT dθT/dt = Qliquid + PT − QCDU and CF dθF/dt = PF + QCDU − Qplant. C = volume × density × specific heat. Temperature deviations θ are relative to the initial operating state. QCDU = Qliquid + PT + G(θT − θF) while both loops circulate; G is the entered per-rack effective coupling conductance multiplied by rack count. The TCS supply rises only with its own stored energy. Initial FWS temperature is derived from the same conductance and running duty.

The 65 kW/(K·rack) CDU conductance, 250 L and 2,000 L inventories, 170 kW recovery margin, 45 s generation delay and 15 s restart are selected training values, not equipment specifications or representative industry defaults. The plant rejects no liquid heat during transfer. After restart, it removes running duty plus a temperature-controlled recovery load, capped by the entered margin. Facility-volume sizing numerically solves this coupled model for the 45°C TCS reference, over the displayed simulation window, assuming adequate UPS energy and zero transfer gap. The window covers at least five minutes and at least three minutes after plant restart. A blank sizing result means no solution within the entered model's 20,000 L search range or no temperature headroom. Bulk-loop temperatures describe this mixed-inventory calculation; gaps indicate no circulation. The residual-air unit has an independent condenser auxiliary.

Same rack load. Three cooling-power arrangements.

Calculated under the current fluid, transfer, UPS and buffer assumptions
Power arrangementNo TCS flow · sPeak flowing supply · °CAbove 45°C · sLiquid / air unserved · kWhNominal UPS required · kWh
Calculation source ↓

Air distribution and rack-inlet temperature

Case A resolves the distribution of heat and supply air across four analytical rack zones. The server airflow is sized at the 192 kW design heat and retained as the operating load changes; this is different from the operating-flow sizing shown in the architecture tool. Supply-air allocation and recirculation determine local inlet mixing, while a cooling-capacity shortfall stores heat in the hall.

In the separately named 85%-load airflow exercise at 20°C supply, the chosen 25% open-aisle and 4% contained recirculation inputs reduce the hottest modeled inlet from 23.40°C to 20.43°C. A duty-unit outage increases the contained case’s transient peak to 23.66°C before recovery. At the reference fan setting, proportional server heat and server airflow make all four inlet temperatures equal. The additional 40%-fan example exposes unequal supply allocation: the least-supplied zones recirculate more hot exhaust. These comparisons use identical rack loads, fan settings and a 30°C outdoor condition, showing sensitivity to the selected analytical mixing assumptions. These are calculated comparisons, not measured or CFD results. The main architecture exercise starts at 100% operating load with a separate 110% sizing allowance.

The analytical system boundary links four rack zones to a shared cooling bank. Containment and delivered air determine mixing; capacity margin determines stored heat during an outage.
Interactive tool · Airflow, containment and rack-inlet temperatures

Interactive tool · calculated thermal scenarios

Operate the data hall.

Change the load, supply temperature, airflow, and containment. Compare rack-zone inlet temperatures, cooling margin, and a four-minute unit outage.

24 racks · four analytical zones3 units active
Hot return aisle ↑
R1R2R3R4R5R6R7R8R9R10R11R12
→ Cold supply aisle ←
R13R14R15R16R17R18R19R20R21R22R23R24
Hot return aisle ↓
Zone 120.4°C
Zone 220.4°C
Zone 320.4°C
Zone 420.4°C
IT heat load163.2 kW
Cooling capacity margin62.4 kW
Modeled cooling + fans54.7 kW

Hottest inlet · 15-minute event

05915 min35°C16°C27°C reference

How the calculation works +

Four rack zones use sensible heat balance and selected recirculation fractions (open 25%, partial 12%, contained 4%). The resulting approximately 3 K containment difference is an analytical mixing sensitivity to these inputs, not measured or CFD evidence. Equal zone inlet values occur when the proportional server flow and heat give the same rack temperature rise and every zone receives enough air. Lower fan speed exposes the unequal air-delivery allocation. The mixing rise is r/(1-r) × rack temperature rise. Capacity and COP follow explicitly assumed outdoor-temperature curves. The transient combines a 40-second mixing response with a 6 MJ/K effective hall heat capacity. Zone colors show calculated zone averages. The 80 kW modules, outdoor derate of 1.2% per K above 25°C, COP curve, 40 s mixing response and 6 MJ/K thermal store are selected training values, not common industry or manufacturer performance.

The temperature comparison uses the ASHRAE A1-A4 recommended dry-bulb inlet range of 18-27°C.

Equations, inputs, scenario table, and references
Seven reference cases and model equations

Six reference scenarios

ScenarioIT loadUnit-state capacity marginPeak inlet (15 min)
Contained · normal163.2 kW62.4 kW20.43°C
Open aisles · normal163.2 kW62.4 kW23.40°C
Contained · unit outage163.2 kW-12.8 kW23.66°C
Contained · standby replacement163.2 kW62.4 kW20.43°C
Contained · unequal delivery at 40% fan163.2 kW62.4 kW27.61°C
Contained · full design load192.0 kW33.6 kW20.50°C
Contained · 120% load / unit outage230.4 kW-80.0 kW27.89°C

Calculated from the shared model and reference inputs. Capacity margin refers to the selected unit state; peak includes the complete event.

Rack heat balance

ΔT rack = Q IT / (ρ × cp × server airflow)

Inlet mixing

T inlet = T supply + r / (1 - r) × ΔT rack

Recirculation and air delivery

r = r baseline + (1 - r baseline) × max(0, 1 - supply flow / server flow)

Fresh-air heat transfer

Q IT = ρ × cp × fresh airflow × (T exhaust - T supply)

Stored heat

dT bulk / dt = (heat load - heat removed) / C hall

Fan power

P fan = active units × 5 kW × speed³

Simulation and BIM evidence

A native EnergyPlus 24.2 benchmark checks the fixed 163.2 kW airflow-reference load in a 400 m², 3 m-high adiabatic zone. A fixed 163.2 kW internal gain operates for a 24-hour design day, and an ideal sensible-cooling system holds the zone at 20°C. The native hourly output reconciles against 3,916.8 kWh of supplied IT heat. This check isolates the heat balance; fan, compressor and annual weather effects are separate model boundaries. The software handoff below also regenerates equipment and load schedules from the edited labs and supplies an unrun air-side EnergyPlus input. The completed fixed benchmark stays distinct from those editable inputs.

Simulation and BIM workflow

Connect calculations to system design.

Geometry, plant operation and thermal response require different engineering models. The comparison below explains the inputs and outputs associated with each software role. The downloadable schedules provide a common numerical basis with explicit units and assumptions.

Each export regenerates equipment duties and counts, separate air/liquid hourly inputs, weather and water setpoints, and the selected event traces. Revit uses the equipment schedule; IES VE and eQUEST use the load and condition schedules for manual configuration. An editable EnergyPlus IDF contains an ideal air-side sensible balance for the selected air load and outdoor design point. These files are inputs, not completed native runs. Liquid heat remains in its separate schedule. The power-transfer and four-zone exercises retain their own explicitly named cases.

Native EnergyPlus 24-hour sensible load and ideal cooling comparison, both approximately 163.2 kW on a zero to 180 kW scale.
EnergyPlus 24.2 native run, 28 October 2026. Case A supplies 3916.8000 kWh of sensible IT heat; ideal sensible cooling removes 3916.8003 kWh. The small solver residual checks the controlled sensible-energy balance. This ideal-load test evaluates a fixed adiabatic zone, separately from equipment efficiency, airflow mixing and transfer continuity. All 24 reported hourly zone temperatures are 20°C to numerical precision. The run completed with zero warnings and severe errors.
Software roles, common inputs and design outputs

Revit

Coordinate the physical system

Model inputs
Rack and cooling-equipment schedules, electrical demand, pipe connections, duty/standby groups and access zones.
Engineering output to produce
A coordinated BIM layout, equipment schedules and distribution diagrams.
Software documentation ↗

IES VE

Evaluate annual plant operation

Model inputs
IT-load profiles, separate liquid and room-air loads, water temperatures, plant efficiencies, weather and control sequences.
Engineering output to produce
Hourly plant energy, heat rejection and cooling performance under the selected weather file.
Software documentation ↗

eQUEST

Benchmark conventional air cooling

Model inputs
The generic air-cooled cases, zone sensible loads, schedules, fan power and DX or chilled-water efficiencies.
Engineering output to produce
A conventional air-system annual-energy benchmark for comparison with the same load basis.
Software documentation ↗

EnergyPlus

Build a reproducible system benchmark

Model inputs
The common heat loads, schedules, plant assumptions and separate air/liquid heat balance, with explicitly modeled components.
Engineering output to produce
A native input model and hourly results reconciled against the reference heat balances.
Software documentation ↗

The interactive tools use the linked analytical models. The native EnergyPlus output above is a separate sensible-load reconciliation. Revit, IES VE and eQUEST describe complementary software roles; the fixed one-rack schedule package supplies their common input basis. Its schedules contain equipment loads, flow requirements and event traces for comparison across BIM and energy models. A CFD analysis uses geometry, airflow boundaries and heat loads to resolve spatial temperatures and hotspots.

Design criteria and standards

Equipment documentation sets the selected rack’s operating reference; environmental guidance sets the air-inlet comparison. Infrastructure standards organize different assessments, including energy, safety, maintenance and fault tolerance. The applied register below ties each criterion to a calculation, input or required design record. Published editions identify the reference documents; adopted codes and permit requirements depend on the actual site jurisdiction.

Design basis · standards and evidence

Connect each requirement to a design decision.

The review starts with the project jurisdiction and selected equipment. Each reference below identifies the evidence needed for its assessment. The current lab supplies heat balances, flow requirements and capacity-event comparisons.

Applied criteria for the named reference cases · model checks are distinct from code compliance
CheckCriterion / sourceEvidenceInterpretation
Case A rack inlet27°C upper recommended dry-bulb reference (ASHRAE A1–A4)20.43°C contained normal; 23.66°C contained outage peakBelow the selected dry-bulb reference. Humidity and equipment class are separate environmental checks.
Case B TCS design flowNVIDIA DSX ≥1.5 L/min per design kW330 kW × 1.5 = 495 L/minDesign-flow floor applied; fluid properties and pressure loss remain explicit inputs.
Case B inlet conditionNVIDIA published 45°C liquid-cooling design point40°C initial TCS; 41.85°C peak in 5 minutesBelow the selected inlet reference in the backed case. This reference is not an automatic plant-trip condition.
Cooling power continuityMaintain flow, temperature reference and residual-air cooling through transfer0 s no-flow; 0 kWh air shortfall; 0.195 kWh nominal UPS for a 60 s bridgeAll three selected cooling functions maintained in the reference calculation.
Infrastructure topologyUptime Tier objectives and, separately, ANSI/TIA-942-CMatched-delay component/route tests, including planned isolation and a shared dependencyCooling outcomes are evaluated by function. Whole-site Tier certification and TIA rating follow their own assessment frameworks.
Energy and safety design recordsASHRAE 90.4-2025; ASHRAE 15/34; NFPA 70, 75 and 110 as applicableDesign-point heat/power, native heat-balance record, distribution and transfer assumptionsAnnual infrastructure energy, refrigerant/charge, electrical protection and emergency-system classification require the selected equipment and site design basis.
Jurisdiction and editionsAdopted building, mechanical, fire, plumbing, electrical and energy codesConcept engineering basis; no construction site assignedThe construction design establishes adoption dates, amendments, authority having jurisdiction and applicable clauses.
Standards, equipment coordination and evidence register

Design-basis selection

Jurisdiction and adopted codes

Building, mechanical, plumbing, fire, electrical and energy codes ↗

A project location establishes the applicable editions, local amendments and authority having jurisdiction. Published editions and adopted requirements are recorded separately.

Evidence to inspect
Location, adoption record, occupancy/use, equipment arrangement and review of applicable clauses.

Selected-condition calculations

Equipment environmental conditions

ASHRAE TC 9.9 guidance + equipment manufacturer limits ↗

Air inlet, humidity, dew point and liquid temperature ranges are selected for the actual IT equipment class. Recommended and allowable conditions serve different purposes.

Evidence to inspect
Rack-inlet conditions, fluid properties and temperatures, selected equipment limits and dew-point margin.

Energy-method reference

Infrastructure energy

ANSI/ASHRAE 90.4 ↗

The energy assessment addresses the relevant mechanical and electrical infrastructure methods in the selected edition. A single design-point power balance is one input to that assessment.

Evidence to inspect
Applicable edition, weather/load profiles, part-load curves, component energy and electrical-loss boundary.

Equipment-specific review

Refrigeration safety

ASHRAE 15 and 34 + adopted mechanical provisions ↗

DX and chiller selections connect refrigerant safety classification to system location, charge, ventilation and the applicable protection measures.

Evidence to inspect
Refrigerant, charge, machinery-room/occupied-space arrangement and equipment documentation.

Coordination reference

Fire and electrical coordination

NFPA 75 + applicable adopted fire/electrical requirements ↗

Cooling pipework, immersion equipment, electrical supplies, detection and shutdown sequences must be coordinated with fire protection and maintenance access.

Evidence to inspect
Equipment listing/documentation, fluid characteristics, fire strategy and power/control diagrams.

Topology scenario checks

Resilience and maintainability

Uptime Tier criteria or ANSI/TIA-942-C rating framework ↗

Capacity redundancy, distribution paths, shared dependencies and maintenance states are evaluated together. N+1 and 2N describe arrangements; a Tier or rating requires assessment of the complete infrastructure.

Evidence to inspect
A/B paths, isolation points, power dependencies, failure scenarios and integrated testing.

Component-selection reference

Liquid-system integration

OCP cooling specifications + manufacturer requirements ↗

Fluid compatibility, cleanliness, connections, filtration, leak detection and CDU interfaces are part of specifying a working liquid-cooling installation.

Evidence to inspect
Fluid specification, material compatibility, loop pressure/flow, connection and maintenance requirements.
Reference register · reviewed 28 October 2026

ASHRAE lists Standard 90.4-2025 as its published data-center energy standard. TIA lists revision C, May 2024. The applicable project editions and amendments are established through jurisdictional and contractual review.

Results and engineering decisions

The results distinguish three design decisions. Containment improves rack-inlet conditions by limiting recirculation. Redundant capacity and distribution determine how much heat can still be removed during a fault. Cooling backup power and coupled thermal inventory determine whether circulation and supply temperature remain controlled during generator transfer.

In the default 192 kW comparison, N uses three 80 kW duty paths. One module failure leaves 160 kW for 240 seconds, accumulating 2.133 kWh of cooling shortfall. N+1 restores the duty after a 30-second pickup, reducing shortfall to 0.267 kWh. The same single-failure result for N+2 reflects an unused second spare; its value appears when a component is already under maintenance. These results demonstrate why capacity reserve does not guarantee continuity. In the 85%-load airflow reference, the approximately 3.0°C containment benefit is an inlet-mixing result, while the 23.66°C unit-outage peak includes the timed thermal response. In Case B, maintaining both coolant loops and residual-air cooling through the 60-second bridge avoids the flow interruption present without cooling UPS support. Inspect the comparison below for the calculated peak, energy requirement and sensitivity to inventory. Every result remains attached to its named case and explicit assumptions.

Reference results and their design consequence

Airflow reference · 24 racks · 85% load · 163.2 kW

At the reference load, the selected recirculation assumptions lower the hottest inlet by approximately 3.0°C (23.40°C open versus 20.43°C contained). The contained unit-outage trace peaks at 23.66°C. This analytical mixing sensitivity uses 25% open-aisle and 4% contained recirculation; the main sizing lab is a separate 100%-operating-load case.

Transfer reference · one NVL72 rack · 330 kW

With both loops and air cooling backed, the model retains flow and reaches 41.8°C peak flowing TCS supply during the 5-minute window. The 60-second bridge requires 0.19 kWh nominal battery energy at the entered usable fraction and conversion efficiency.

Case B · 40°C initial TCS · 250 L technology inventory · 2,000 L facility inventory · 65 kW/K effective coupling · 1 kWh cooling UPS
Cooling backupNo TCS flow · sPeak flowing TCS · °CLiquid / air heat unserved · kWh
No cooling UPS60.0Interrupted: 60.0 s without flow. 40.00°C while flowing only5.390 / 0.110
Technology pump only0.058.68°C0.000 / 0.110
Both loops + residual air0.041.85°C0.000 / 0.000

The coupled model solves approximately 596 L of facility volume for the 45°C TCS reference over this window, assuming uninterrupted power to both loops and the air unit. This value depends on the 250 L technology inventory, effective CDU conductance, initial temperatures and recovery control. The 2,000 L reference buffer is evaluated with those same assumptions.

Sensitivity to connected buffer volume and CDU coupling

These half-to-double ranges bracket the selected 2,000 L participating facility inventory and 65 kW/(K·rack) effective CDU coupling. They illustrate model sensitivity, not measured equipment variation. Every row keeps one 330 kW rack, 250 L technology inventory, 40°C initial TCS supply, a 60 s transfer, 170 kW recovery margin and the 1 kWh both-loop/air UPS. Initial facility temperature is recalculated consistently with each conductance.

Same continuous-cooling model and five-minute window
Facility inventory · LCDU coupling · kW/(K·rack)Peak flowing TCS · °CAbove 45°C · sNo flow · s
100032.543.00.00.0
10006543.30.00.0
100013043.60.00.0
200032.541.80.00.0
20006541.80.00.0
200013042.00.00.0
400032.541.00.00.0
40006541.00.00.0
400013041.00.00.0
Download sensitivity values and units ↓

The resulting design sequence is to control recirculation, size the liquid and air paths independently, verify the response of every serial component, and test cooling power continuity with finite battery energy. A sustainable IT capacity, an actual heat-removal rate and an IT shutdown are distinct results throughout the calculations.

Contact

Do you have a question or want to chat?

Analytics preferences

Optional Google Analytics uses cookies to measure page visits and engagement. You can browse the entire portfolio with analytics off.

Analytics is off in this browser.

Privacy details. Change your choice here at any time. Your preference is remembered for up to 180 days.